Harris County Low Impact Development & Green Infrastructure Design Criteria for Storm Water Management

CountyTexasmediumNeeds reviewCitations verified

This extraction is flagged for quality review.

Compare each cited field to the official PDF before relying on it. What this means

LID/GI design criteria (2011). Full HCFCD PCPM remains portal-gated; this PDF covers SWQ 1" treatment and LID IMPs used with county detention criteria. Pipeline excerpt repair removed 4 unlocated citation(s).

Fields not found in document: design_criteria.design_storm_return_periods_years, design_criteria.required_hydrologic_hydraulic_software, document_metadata.jurisdiction_level, document_metadata.version_or_edition, document_metadata.adoption_or_effective_date, document_metadata.last_revised_date

Document Metadata

Jurisdiction level
Not found in document

No evidence cited

State
Texas

Harris County Flood Control District

Cover

Version / edition
Not found in document

No evidence cited

Adoption / effective date
Not found in document

No evidence cited

Last revised date
Not found in document

No evidence cited

Relationship to state manual
independent

interim guidelines ... HCPID-AED and HCFCD Storm Water Management Programs

Background

Design Criteria

Design storm return periods (years)
Not found in document

No evidence cited

Water quality volume method
Projects exceeding one acre require a Storm Water Quality (SWQ) Permit and SWQMP; treat the first 1 inch of runoff. LID IMPs (bioretention, vegetated swales, permeable pavement, rainwater harvesting, green roofs, filter strips, planters, tree box filters) may satisfy quality and detention credits per Table 1. Conventional gravity detention minimum rate 0.55 ac-ft per acre (Table 3); LID projects may use reduced detention with approved low-impact approach.

Treatment of the first 1" of runoff ... Storm Water Quality Permit required

Table 5 / §2.4

Peak flow calculation method(s)
Detention and hydrograph matching per HCPID-AED / HCFCD requirements, Minimum detention 0.55 ac-ft/acre for gravity systems

The minimum detention rate for gravity drained detention basin systems is 0.55 ac-ft

Table 3

Hydrologic/hydraulic software
Not found in document

No evidence cited

Approved BMP categories
Disconnection of roof runoff and impervious surfaces, Vegetated filter strip, Vegetated swale / bioswale, Rainwater harvesting, Bioretention systems, Permeable pavement, Tree box filter, Storm water planter box, Green roof

Roof Runoff & Impervious Surfaces 3.2 Vegetated Filter Strip 3.3 Vegetated Swale 3.4 Rainwater Harvesting 3.5 Bioretention Systems 3.5.1 Requirements 3.5.2 Sizing a Bioretention system 3.5.3 Engineered Soil Media 3.5.4 Underdrain 3.5.5 Observation/Cleanout Pipe 3.5.6 Positive O

p. 2