Stormwater Atlas

City of Santa Barbara

Storm Water BMP Technical Guidance Manual

CityCaliforniahighNoCitations verified
Fields not found in document: design_criteria.design_storm_return_periods_years

Document Metadata

Jurisdiction level
City

No evidence cited

State
California

No evidence cited

Version / edition
December 2020

No evidence cited

Adoption / effective date
Not found in document

No evidence cited

Last revised date
2020-12

No evidence cited

Relationship to state manual
independent

No evidence cited

Design Criteria

Design storm return periods (years)
Not found in document

No evidence cited

Water quality volume method
Tiered SWMP requirements by new/redeveloped impervious area. Tier 4: retain/prevent offsite discharge for storms up to the 95th percentile 24-hour rainfall event (currently 2.4" for Santa Barbara); retain 1.2" 24-hour for replaced impervious and 2.4" for new impervious. Tier 3: peak runoff discharge rate and water quality treatment; volume reduction per Ch.6. Volume reduction that exceeds water quality treatment volume also satisfies treatment if BMPs treat runoff.

95th percentile 24-hour rainfall event, which is currently 2.4" for Santa Barbara

§1.4 / Tier 4

Peak flow calculation method(s)
Peak runoff discharge rate matching for Tier 3/4, BMP sizing worksheets (Ch.6)

No evidence cited

Hydrologic/hydraulic software
Not found in document

No evidence cited

Approved BMP categories
Bioretention / planter boxes, Permeable pavement, Infiltration basins / trenches, Rain barrels / cisterns, Bioswales / vegetated BMPs, Dry extended detention, Other Ch.6 Storm Water Runoff BMPs

No evidence cited