Stormwater Atlas

Suwannee River Water Management District (SRWMD)

Environmental Resource Permit Applicant's Handbook Volume II (Design Requirements for Stormwater Treatment and Management Systems)

Special DistrictFloridahighNeeds reviewCitations verified

This extraction is flagged for quality review.

Compare each cited field to the official PDF before relying on it. What this means

Canonical SRWMD ERP AH Vol II special_district record. City proxy gainesville-fl remains for municipal map coverage.

Fields not found in document: design_criteria.required_hydrologic_hydraulic_software

Document Metadata

Jurisdiction level
Special District

Florida water management district (ERP Applicant's Handbook Volume II)

Chapter 62-330, F.A.C. / district handbook

State
Florida

Incorporated by Reference in Rules 62-330.010 and 40B-400.091, F.A.C.

Title Page

Version / edition
Effective July 2024

Effective July 2024

Title Page

Adoption / effective date
2024-07

Effective July 2024

Title Page

Last revised date
2024-07

Effective July 2024

Title Page

Relationship to state manual
adopts state manual directly

This Volume provides specific, detailed information to meet the water quality system and quantity design requirements of stormwater management systems. ... Both Applicant's Handbook Volumes I and II are adopted by reference in Chapter 62-330, F.A.C.

Section 1.1.1 Introduction

Design Criteria

Design storm return periods (years)
10-year, 25-year, 100-year

For projects which serve exclusively agricultural, forest, conservation, or recreational land uses, a design storm with a 10-year, 24-hour rainfall depth with SCS type II distribution ... shall be used. For projects which serve all other land uses, a design storm with 100-year critical duration rainfall depth with SCS type II distribution ... shall be used.

Section 3.2 Design Storms

Water quality volume method
Minimum State water quality treatment requirements are those in statewide ERP Applicant's Handbook Volume I; Volume II requires all systems to recover treatment volumes within 72 hours (retention may use only percolation and evaporation; detention with filtration needs a safety factor of two). Quantity retention in closed basins is post- minus pre-development runoff for the 100-year critical event (max one-day duration). Flood storage recovery: one-half of total volume within seven days and total volume within 30 days after each design storm.

All stormwater management systems must be designed to provide minimum State water quality treatment requirements as set forth in Applicant's Handbook Volume I.

Section 4.3 State Water Quality Standards

Peak flow calculation method(s)
Pre- and post-development runoff hydrographs with detention/retention routing (stage-storage-discharge), Rational Method, Natural Resources Conservation Service (NRCS) method, USGS regression equations, SCS Type II distribution on average antecedent moisture conditions, Peak Rate Factor (K') method (conservative post-development K'=484)

There are several equations available for calculating discharge including, but not limited to, the Rational Method, Natural Resources Conservation Service (NRCS) method, and USGS regression equations.

Section 3.3.1 Methodologies for Calculating Discharge

Hydrologic/hydraulic software
Not found in document

No evidence cited

Approved BMP categories
Retention ponds, Dry detention ponds, Exfiltration trench systems, Wet detention ponds, Swale systems, Vegetated natural buffers, Borrow pits and ponds, Dams and impoundments, Sensitive karst area BMPs

The Best Management Practices (BMP)s below are the most frequently used BMPs in this District.

Part V – Best Management Practices