Stormwater Atlas

City of Murfreesboro

Stormwater Planning & Low Impact Design Guide

CityTennesseemediumNeeds reviewCitations verified

This extraction is flagged for quality review.

Compare each cited field to the official PDF before relying on it. What this means

Primary planning/LID guide (Apr 2008). Structural Controls Manual is published as separate CivicPlus DocumentCenter sections. Pipeline excerpt repair removed 1 unlocated citation(s).

Fields not found in document: design_criteria.required_hydrologic_hydraulic_software, document_metadata.version_or_edition

Document Metadata

Jurisdiction level
City

No evidence cited

State
Tennessee

No evidence cited

Version / edition
Not found in document

No evidence cited

Adoption / effective date
2008-04-01

No evidence cited

Last revised date
2008-04-01

No evidence cited

Relationship to state manual
independent

independent city LID / planning guide

Coverage note

Design Criteria

Design storm return periods (years)
100-year

the full build-out 100year storm event is to be conveyed on-site such that no resulting habitable structural flooding occurs

Table 1.2-1 Step 3

Water quality volume method
WQv = 1.2 * Rv * A / 12 (acre-feet). Treat runoff from rainfalls up to 1.2 inches (85th percentile / Middle Tennessee). Streambank Protection Volume (SPv): controlled release of the 3.1-inch storm over 24 hours. Flood control: convey full build-out 100-year on-site without habitable structural flooding; downstream options per assessment.

WQv = 1.2 * Rv * A / 12 ... 1.2 inches of rainfall has been identified as the average depth corresponding to the 85th percentile storm for the Middle Tennessee region

§1.2.2.1

Peak flow calculation method(s)
Water Quality Protection Volume (WQv), Streambank Protection Volume (SPv) — 3.1-inch / 24-hr release, Downstream hydrologic analysis for flood control

Provide on-site controlled release of the 3.1” storm event over a period of 24 hours (Streambank Protection Volume, SPV)

Table 1.2-1 Step 2

Hydrologic/hydraulic software
Not found in document

No evidence cited

Approved BMP categories
Site design / LID practices (conserve natural features, reduce imperviousness), Structural stormwater controls (WQv / SPv / flood), Detention facilities with multi-step outlet controls

No evidence cited