Design Standards for Stormwater Detention and Retention

CountyArizonahighNo
Other manuals in Arizona: City of Phoenix, City of Tucson

Document Metadata

Jurisdiction level
county

runoff detention and retention systems are required for development in Pima County... management regulations throughout the jurisdictions of Pima County

Section 1.1

State
Arizona

Tucson, AZ 85701-1791

Cover

Version / edition
First Edition June 2014; Chapter 6 revised February 2015

First Edition June 2014... Chapter 6 Revised to Include Benefits of Multiple-Use Basins February 2015

Revisions

Adoption / effective date
2014-06

First Edition June 2014

Revisions / Cover

Last revised date
2015-02

Chapter 6 Revised to Include Benefits of Multiple-Use Basins February 2015

Revisions

Relationship to state manual
independent

Supplement to Title 16, Chapter 16.48, Runoff Detention Systems Floodplain and Erosion Hazard Management Ordinance

Cover

Design Criteria

Design storm return periods (years)
2-year, 10-year, 100-year

New development located within a Balanced Basin must provide sufficient detention to reduce the post-developed 2-, 10- and 100-year peak discharge rates to the pre-developed rates.

Section 1.2

Water quality volume method
First-flush retention: capture and retain runoff from 0.5 inch of rainfall on newly disturbed or impervious areas (85th percentile storm). Required volumes by land type from SCS Curve Number method (e.g., 1440 ft³/ac impervious on lower-permeability areas; 1815 ft³/ac on mapped riparian/higher-permeability areas).

First-flush retention is defined as the capturing and retaining of the stormwater runoff volume from 0.5 inch of rainfall on all newly disturbed or impervious areas for new development or redevelopment

Section 1.5, Page 5

Peak flow calculation method(s)
PC-Hydro, Pima County Technical Policy TECH-015 (Acceptable Methods for Determining Peak Discharges), Pima County Technical Policy TECH-018 (Acceptable Model Parameterization), City of Tucson Standards Manual for Drainage Design and Floodplain Management (where applicable), HEC-HMS (basin routing)

The pre-developed conditions peak discharge rates for each return period shall be established using the modeling methods described in the District's Technical Policy, TECH-015, Acceptable Methods for Determining Peak Discharges, and Technical Policy, TECH-018

Section 3.2.1, Page 21

Required hydrologic/hydraulic software
PC-Hydro, PC-LID spreadsheet, HEC-HMS (Version 3.3 or higher acceptable for basin routing)

Volumes of each basin were calculated using the PC-LID spreadsheet.

Section 2.2 Example, Page 12

Approved BMP categories
Detention Basins, Stormwater Harvesting Basins, Roadside Stormwater Harvesting Basins, Bioretention Basins, Retention within Detention Basins, Pervious Pavements (porous gravel, concrete grid, PICP, pervious concrete), Dry Wells, Low Impact Development (LID) Practices

5.3 Stormwater Harvesting Basins... 5.4 Roadside Stormwater Harvesting Basins... 5.7 Bioretention Basin... 5.8 Retention within a Detention Basin... 5.9 Pervious Pavements... Porous Gravel... Concrete Grid Pavement... Permeable Interlocking Concrete Pavement... Pervious Concrete... 4.19 Dry Wells