City of Chicago
Stormwater Management Ordinance Manual
Document Metadata
“City of Chicago”
Cover
“Chicago, Illinois 60602”
Page 3, Section 1.4
“August 2024”
Cover
“August 2024”
Cover
“August 2024”
Cover
“The purpose of this 'Stormwater Manual' (Manual) is to help applicants understand and comply with the Ordinance and accompanying Chapter III 'Requirements for Stormwater Management' of the 'Regulations for Sewer Construction and Stormwater Management' (Regulations).”
Page iv, Foreword
Design Criteria
“Velocities must be 1 ft/sec or less during the 2-year storm event... minor drainage systems for small storm events of up to the 5-year storm event... storage for a minimum 10-year event... 25-year storm analysis... 100-year storm event”
Pages 7, 14, 24, 36, 39
“Capture one-half inch of runoff from all impervious surfaces in accordance with volume control BMPs; or (B) For Developments that do not directly discharge to Waters or to a municipal separate storm sewer system, achieve a fifteen-percent reduction in impervious surfaces from existing conditions.”
Page 26, Section 3.2
“Modified Rational Method to calculate the maximum volume of stormwater... Rational Method... hydrograph methods with regional rainfall data... HEC-1 and HEC-HMS... TR-20... TR-55... SWMM”
Pages 7, 15, 16, B-6, B-7
“The initial site plans, Stormwater Management Plan (SMP), Stormwater Spreadsheet Tool and all other supporting documentation must be submitted to DOB”
Page 3, Section 1.4
“Green Roofs... Rooftop Runoff BMPs (Planter Boxes, Rain Barrels and Cisterns)... Permeable Paving... Natural Landscaping... Vegetated Filter Strips... Bioinfiltration Systems... Drainage Swales... Infiltration Vault”
Page 36, Section 3.3.1