Compare each cited field to the official PDF before relying on it. What this means

Construction ESC training course manual (Oct 2024), not a post-construction hydrologic design manual. Only explicit design storm is the 2-year/24-hour precipitation event for temporary ESC controls (manual + appended SDDANR CGP). No water quality volume sizing, peak-flow hydrology methods, or required modeling software found in the text.

Fields not found in document: document_metadata.adoption_or_effective_date, design_criteria.water_quality_volume_method, design_criteria.peak_flow_calculation_method, design_criteria.required_hydrologic_hydraulic_software
Other manuals in South Dakota: City of Pierre, City of Sioux Falls

Document Metadata

Jurisdiction level
State

SDDOT's Construction activities fall under the provisions of the SDDANR General Permit for Stormwater Discharges Associated with Construction Activities... manage the NPDES in South Dakota.

Page 4

State
South Dakota

South Dakota Department of Transportation (SDDOT)

Page 1

Version / edition
Revised October 2024

EROSION & SEDIMENT CONTROL Revised October 2024

Cover / Table of Contents

Adoption / effective date
Not found in document

No evidence cited

Last revised date
2024-10

Revised October 2024

Cover

Relationship to state manual
independent

The information in this training manual is intended for training purposes only and does not take precedence over the SDDOT Standard Specifications for Roads and Bridges, the SDDOT Materials Manual, or any SDDOT Policies and Procedures.

Page 1

Design Criteria

Design storm return periods (years)
2-year

All sediment and erosion controls shall be selected, designed, and installed to function properly and withstand a 2 year/24-hour rain event.

Page 4

Water quality volume method
Not found in document

No evidence cited

Peak flow calculation method(s)
Not found in document

No evidence cited

Hydrologic/hydraulic software
Not found in document

No evidence cited

Approved BMP categories
Erosion Control BMPs (Temporary/Permanent Seeding, Mulch, Erosion Control Blanket, Flexible Channel Liner, Bonded Fiber Matrix), Slope Flow Control / Stormwater Runoff Management (Diversion Berm, Diversion Swale, Pipe Slope Drain), Slope and Channel Velocity Controls (Rock Check Dam, Rock Rip Rap, Wattles), Outlet Protection, Sediment Control BMPs (Silt Fence, Inlet Protection, Perimeter Control, Sediment Trap, Sediment Basin), Stabilized Construction Entrance/Exit, Dewatering Sediment Capture BMPs and Flocculants

Erosion Control BMP's... Slope Flow Control/Stormwater Runoff Management... Slope Velocity Controls... Channel Surface Control... Channel Velocity Control... Outlet Protection... Sediment Control BMP's... Inlet Protection... Perimeter Control... Stabilized Entrance Protection

Table of Contents, Chapter 3