State of Hawaii Department of Transportation, Highways Division
Storm Water Post-Construction Best Management Practices Manual
Document Metadata
“State of Hawaii Department of Transportation Highways Division”
Title Page
“State of Hawaii Department of Transportation”
Title Page
“December 2021”
Title Page; Record of Revision
“Revision No. 1 December 2021 Revised criteria for MS4 NPDES Permit areas”
Record of Revision
“Revision No. 1 December 2021”
Record of Revision
“Private construction projects located outside the DOT-HWYS right-of-way are considered to be in compliance with post-construction BMP requirements if the project complies with the storm water quality requirements of the applicable county.”
Section 3.1.3, Page 3-3
Design Criteria
No evidence cited
“WQV = P x C x AT x 3630 Where WQV = Water Quality Volume (ft3) P = Design Storm Runoff Depth (inches) = 1 inch”
Section 7.3.1, Page 7-6
“Flow rate calculation shall be based upon the Rational Method as follows: WQFR = C x i x AT”
Section 7.3.2, Page 7-7
No evidence cited
“LID TREATMENT CONTROL BMPs: Vegetated Buffer Strip, Vegetated Swale, Enhanced Swale, Infiltration Trench, Infiltration Basin, Bioretention Facility, Permeable Pavement, Pocket Wetland, Rainwater Harvesting, Tree Box Filter”
Appendix A, Page v