City of Baltimore
Stormwater Management Minimum Requirements
Document Metadata
“Article 7, Division II of the City Code requires that land disturbance activities must have stormwater management plans approved by the Department of Public Works (DPW).”
Page 1
“comply with the 2000 Maryland Stormwater Design Manual (Revised)”
Page 1
“Baltimore City DPW October 2019”
Page 1
“Baltimore City DPW October 2019”
Page 1
“Baltimore City DPW October 2019”
Page 1
“The stormwater management plans must also comply with the 2000 Maryland Stormwater Design Manual (Revised)”
Page 1
Design Criteria
“Channel protection volume (CPV): 24-hour extended detention of a one-year storm... Overbank flood protection volume (Q10): control of the peak flow rate of a 10-year storm... Extreme flood volume (Q100): control of the peak flow rate of a 100-year storm”
Page 4
“New development Treatment of 1.0 inch... Redevelopment Treatment of 0.5 inch; or 50% removal of impervious surface area; or Combination of both.”
Table 1, Page 5
“CPV and Q10 are required in all areas, except if directly discharging to tidal areas. Q100 is required for inter-jurisdictional watershed and flood hazard areas noted in this document.”
Table 1, Page 5
No evidence cited
“Proposed stormwater management must demonstrate ESD to the MEP... environmental site design (ESD) must be the first approach in stormwater management design, followed by structural practices then alternative practices.”
Page 4